France’s Court of Auditors says state-owned EDF could struggle to finance six planned reactors, which it estimates will cost €84 billion.

France’s Court of Auditors has warned that state-owned Électricité de France could struggle to finance six planned nuclear reactors, which it estimates will cost €84 billion.

The assessment comes weeks before the utility, known as EDF, is expected to make its final investment decision. France has also announced a 10-year strategy to advance fusion energy research.

EDF faces higher reactor costs

The estimated €84 billion cost for the six EPR2 reactors is about $92.5 billion. EDF previously estimated the program would cost €72.8 billion, or approximately $80.1 billion.

EDF and Framatome developed the reactors. Construction is scheduled to begin in 2027, with the first commercial operations scheduled for 2038.

The plans call for two reactors each at Penly, Gravelines and Bugey. All three sites already have operating nuclear power plants.

Penly is scheduled to host the first EPR2 units and serve as the reference site for the other two locations.

The French government has agreed to provide EDF with a subsidized loan covering 60 percent of the program’s total cost.

It also established a price-support arrangement with a threshold of no more than €100 per MWh. The state would pay EDF when market prices fall below that level.

The Court of Auditors warned that wholesale electricity prices below €70 per MWh would significantly increase the financing needed for construction. EDF could then need state contributions beyond the subsidized loans, the court said.

Wholesale baseload electricity prices for delivery in 2028 and 2029 are projected at €65.75/MWh and €60.10/MWh, respectively, according to the report.

The audit concluded that extending each existing EDF reactor’s operating life to 60 years would be France’s cheapest and most dependable low-carbon energy option.

France sets fusion research goals

Higher Education, Research and Space Minister Philippe Baptiste unveiled the fusion strategy during visits to ITER and the WEST tokamak, a fusion research machine.

The plan centers on work with ITER, WEST and the Laser Mégajoule facility. It also aims to double student numbers in fields including plasma physics, nuclear engineering and cryogenic technologies.

From 2026 to 2030, the strategy calls for strengthening scientific foundations, expertise and experimental facilities, as well as securing funding. It sets a 2035 target for a European pilot fusion power plant to operate.

At ITER, Baptiste said, “We all know the importance of working on fusion, on the future of energy in order to have an energy source that is available and also carbon-free.”