Mumbai-Goa Highway’s 8-km Stretch Hangs Fire as Costs Top Rs 18,100 Crore
Five unfinished stretches in Maharashtra are holding up the Mumbai-Goa highway, which is 99% complete overall. The project’s Maharashtra section has seen its cost estimate rise from Rs 12,532 crore to over Rs 18,100 crore, with officials targeting completion by April 2027.

India’s Ministry of Road Transport and Highways says the Mumbai-Goa highway’s 8-km stretch hangs fire across five unfinished sites in Maharashtra, despite the route being 99% complete overall, with work due by April 2027.
The remaining work is spread across five of the project’s 13 packages. It includes three kilometers of bypasses, a 192-meter bridge, a 1.8-km flyover, hill cutting at four locations over 1.5 km and other road work.
Once crews finish the Maharashtra sections, the highway will connect Mumbai-area Panvel with Panaji, Goa’s capital. The 120-km Goa section from the Maharashtra border to Panaji is complete.
Costs rise as work stalls
The estimated cost of the 472-km Maharashtra section has climbed from Rs 12,532 crore to over Rs 18,100 crore, an increase of around 44 per cent, according to the ministry. Officials attributed the increase mainly to land acquisition, changes required by site constraints and additional underpasses requested by local residents.
Officials and contractors cited cash-flow problems, loan defaults, land acquisition issues and local protests among the reasons for the delays.
The project was conceived in 2006 as a four-lane upgrade of NH-66, planned as an economic corridor from Panvel near Mumbai to Kanyakumari. Construction began in October 2007 on the first 21-km section in Maharashtra near the Goa border; that section opened in 2013.
Most other sections were approved in 2015-16, with contracts awarded in 2017-18. The government told Parliament in December 2016 that the highway would be completed by December 2018, then revised the target to 2021. Some remaining work was re-awarded as late as October 2025.
April 2027 completion target
“In the last two years, a lot of work was done on stalled stretches and 99% of the highway is through now,” V Umashankar, secretary of the Ministry of Road Transport and Highways, said. “All pending work will be completed by April next year.”
At the opening of a 5.15-km corridor in Porvorim, Goa, on September 9, Union Minister of Road Transport and Highways Nitin Gadkari said he was “ashamed for the delay that has happened” and would skip the highway’s inauguration, which was expected next year.
A senior ministry official said the government now requires environmental and forest clearances before tenders are invited, and at least 90% of land acquisition before contracts are awarded.
Take the quizWhat Kind of Holiday Spender Are You? Take the Black Friday QuizStart →- 1I’m A Celebrity 2026 Line-Up: Rooney Leads 11 Stars Into Jungle

- 2Mavericks Surfers Race to California for Waves Near 50 Feet

- 3NYC Medical Examiner Has Not Determined Cause of Death of Beau Rose Jessup

- 4Mountaineer Finds Ice Age Cave Bear Graveyard in the Dolomites

- 5Rugby League World Cup Final 2026: Kick-Off Times and How to Watch Kangaroos v New Zealand

Lifestyle7 Signs Your Social Battery Is Running Low (and Why You Keep Cancelling Plans)
Lifestyle · Food & HealthThanksgiving Food Safety: How Long Leftovers Last and the Safe Turkey Temperature
Lifestyle7 Quiet Habits of Emotionally Intelligent People, According to Psychologists
LifestylePeople Who Don’t Like Celebrating Their Birthday Often Share These 7 Traits