JournalArta
Wednesday, November 18, 2026 · JakartaS&P 7,303.98 ▼0.50%USD/IDR 18,249 ▼0.07%
JournalArta
Global Edition
beyond headlines
Advertisement

FERC Large-Load Rules and US Data Center Power Costs

FERC Section 206 proceedings and PJM co-location rules reshape how US AI data centers price transmission, backup power, and deployment timelines.

By matthew jonathan
November 18, 20265 min read
Editorial illustration of a US AI data center campus beside a high-voltage substation and power generation facility
FERC Large-Load Rules and US Data Center Power Costs)

Co-locating a US data center with a power plant can bring the first AI racks online sooner if the site can operate within its approved grid import limits during a generator outage. For enterprise AI infrastructure buyers planning US data center grid interconnection, FERC proceedings make the transmission service agreement central to both the power budget and the deployment schedule.

  • FERC opened Section 206 proceedings covering six regional grid operators on June 18, 2026, seeking tariff explanations or changes tailored to each region (FERC orders).
  • FERC established certain rates and terms for three new PJM co-location services, including temporary non-firm service while upgrades for full network service are built (FERC, EL26-67).
  • PJM proposed voltage and frequency ride-through requirements for large computing loads on November 16, with a requested effective date of January 16, 2027 (PJM, ER27-522).
Advertisement

What DOE proposed and what FERC ordered

On October 23, 2025, Energy Secretary Chris Wright invoked Section 403 of the Department of Energy Organization Act to direct FERC to initiate rulemaking procedures. DOE's advance notice proposed a scope covering new loads above 20 MW and asked about studying large loads alongside generation where practicable. It also raised standardized study deposits, readiness requirements and withdrawal penalties. Treat the 20 MW threshold as part of DOE's proposal and verify the applicable threshold under the tariff for the site in the DOE direction and advance notice.

FERC's June 2026 show-cause orders asked PJM, SPP, NYISO, MISO, CAISO and ISO New England and their relevant transmission owners to justify or address aspects of their tariffs. In PJM, FERC raised gaps in study transparency, upgrade cost recovery and service options for flexible loads. The new PJM ride-through filing shows how those concerns can reach the equipment specification. Ride-through is the ability to stay connected during a grid disturbance. Ask the utility which requirements apply at the point of interconnection before specifying how the campus will transfer to backup power, per FERC EL26-67 and the PJM filing.

Advertisement

The DOE-funded Berkeley Lab report estimated US data center electricity use at 176 TWh in 2023 and modeled 325 to 580 TWh for 2028 (DOE demand report). The IEA separately estimated global use at 485 TWh in 2025 and projects 950 TWh in 2030 in its central case (IEA demand outlook). For site selection, the local evidence is the utility's phase-by-phase delivery schedule. The same distinction between announced capacity and usable power matters in markets facing Singapore 200 MW data centre power limits.

PJM transmission options and the cost of backup power

FERC's December 2025 PJM order addressed co-location and directed tariff changes (December co-location order). Its June 2026 follow-up established certain rates, terms and conditions for the new services and directed further compliance work. For co-located projects, the service choice determines what grid imports the operator can plan around during a plant outage.

Advertisement
PJM serviceService firmnessUpgrade scopeWhat the project can plan around
Network Integration Transmission Service (NITS)Firm network serviceRequired network upgrades reflected in delivery scheduleFull designated load once required upgrades are completed.
Interim NITSNon-firm temporary serviceUsed while upgrades for full NITS are builtInterim grid imports subject to curtailment until full NITS is ready.
Firm contract demandFirm up to contracted MWSized to contracted capacity commitmentGuaranteed transmission up to contracted MW during normal grid conditions.
Non-firm contract demandAs-available up to contracted MWLower upfront transmission commitmentMust shed load or run onsite generation when transmission is curtailed.
Advertisement

For a colocation data center power bid, ask for separate prices for energy, contracted transmission, required upgrades and onsite backup. Ask who funds construction, when collateral is due and what the tenant owes if it delays or cancels a phase. FERC's PJM show-cause order specifically raised the risk that other transmission customers could inherit costs when a load comes in below plan. Carry those obligations into the cash-flow model alongside the power purchase agreement. Use annualized USD per deliverable IT kilowatt to compare bids, with the same cooling overhead assumptions and service commitments in each scenario. A site-specific tariff bill and upgrade cost are not disclosed in the regional orders.

Advertisement

Nuclear and gas co-location put different equipment on the critical path

In PJM's co-location configuration, the load connects on the generator's side of the grid interconnection point. Geography alone leaves that electrical design open. Talen's June 2025 filing described a plan to move the adjacent Amazon Web Services campus at Susquehanna from direct supply to front-of-the-meter service after transmission reconfiguration. The expanded agreement calls for up to 1,920 MW at full contract quantity through 2042, with the contract's unit price not disclosed in the announcement (Talen filing). For a nuclear-backed bid, ask what remains deliverable during refueling or a trip, who supplies replacement power and which delivery dates depend on switching work.

Advertisement

For gas, GE Vernova and Crusoe announced orders totaling 29 LM2500XPRESS packages in July 2025, expected to provide nearly 1 GW combined. The vendor describes a 35 MW dual-fuel package with an emissions control system and independent startup capability (GE Vernova and Crusoe announcement). For a campus evaluating modular microgrid systems, ask bidders for guaranteed net output at the site's design ambient conditions, firm fuel delivery terms, maintenance coverage and the capacity available with the largest unit out. Price the storage and controls needed to keep critical load online through the transfer. Equipment ratings leave fuel readiness, permitting, protection settings and site acceptance as separate milestones.

Advertisement

Match GPU purchase commitments to deliverable power

Choose full network service or sufficient contracted firm imports when customer uptime obligations leave little room for curtailment. Consider interim or non-firm service for early phases that can shed load, move work or run on dependable onsite supply. Before committing to rack deliveries, get an agreed load ramp, a date for each required upgrade and a tested response to loss of generation at peak campus load.

If the first deployment date precedes utility acceptance, price temporary cloud GPU capacity against the cost of idle owned hardware. As of November 18, AWS listed an effective Capacity Blocks reservation rate of $380.952 per hour for the u-p6e-gb200x36 UltraServer in its US East (Dallas) Local Zone, charged upfront with rates subject to change before purchase (AWS Capacity Blocks pricing). For inference that can use managed services, budget separately using our guide to AI inference cloud costs.

Advertisement

Make the first production date depend on the IT load the site can actually sustain during the agreed outage scenario. Release later hardware orders against verified increments of usable power. That ties capital spending to the capacity the enterprise can put into service.

Advertisement
Take the quizWhat Kind of Holiday Spender Are You? Take the Black Friday QuizStart →
Advertisement
Most Read
  1. 1U.S. Emergency Alert Test Nov. 17 Is Not a Power Outage
  2. 2DUP Chairman Lord Morrow Loses Wife and Daughter Within Hours in NI
  3. 3NASA’s Curiosity Rover Burst Open a Rock and Found Pure Sulfur
  4. 4Women With Autoimmune Diseases Wait About 4 Years for Diagnosis, Study Finds
  5. 5Stock Market Today: Dow Futures Slip as Nasdaq Futures Climb Before Earnings
Advertisement
Don't Miss

Latest News

All stories →
  1. Markets · StocksS&P 500 Futures Rise After Nvidia Raises Sales ForecastNov 18
  2. Markets · StocksAnthropic Investors Can Seek Exposure Without Buying Its IPONov 18
  3. Lifestyle · Food & HealthRASONQUE Wins EU Approval for Treated Pancreatic CancerNov 18
  4. World · EuropeFive EU Countries Agree to Open Rwanda Return HubNov 18
  5. Advertisement
  6. Lifestyle · Food & HealthKate Middleton Visits Maternity Hospital in MumbaiNov 18
  7. Technology · AIOpenAI Shifted 25% of Production Engineers to Security, President SaysNov 18
  8. Lifestyle · EntertainmentLance Bass Shares Twins’ Favorite *NSYNC Christmas SongNov 18
  9. Business · CompaniesTextron Agrees to Sell Industrial Unit for $1.2 BillionNov 18