Indonesia Could Reach 96.7 Gigawatts of Solar Capacity by 2029
Indonesia could expand its solar capacity to 96.7 gigawatts by 2029 if projects advance through several channels and policy obstacles are addressed, a Jakarta-based think tank says. The country had 1.59 gigawatts installed in the first quarter of 2026.

Indonesia could reach 96.7 gigawatts of installed solar capacity by 2029 if development advances through several channels at once, the Institute for Essential Services Reform said in its Indonesia Solar Energy Outlook 2027.
The forecast depends on policy changes. The Jakarta-based think tank said regulatory gaps, procurement uncertainty and limited grid access are holding back deployment.
Indonesia had 1.59 gigawatts of installed solar capacity in the first quarter of 2026. That represented around 1.5% of its power generation capacity and 0.3% of electricity production, the institute said.
Rooftop installations accounted for 0.9 gigawatts. Utility-scale projects contributed 0.33 gigawatts, captive solar supplied 0.3 gigawatts, and remote-area installations accounted for around 0.06 gigawatts.
Projects face procurement and grid barriers
President Prabowo Subianto has set a target of 100 gigawatts of solar power by 2029. The program launched in August with 14 initial projects totaling around 5.2 gigawatts.
Only 526 megawatts of that initial capacity currently have targeted completion dates, the institute said.
Its model includes around 8 gigawatts already planned through the electricity supply business plan and Mentari GigaOne procurements. A further 56 gigawatts could come through purchases by state-owned electric utility PLN.
The remaining 33 gigawatts could come from rooftop solar, diesel replacement, rural electrification, captive solar and other distributed uses, the report said.
Institute CEO Fabby Tumiwa said the 100-gigawatt ambition needs to appear in updates to the 2025-2034 electricity supply business plan. He called for greater emphasis on large solar projects with battery storage, replacing diesel with solar and storage, and rooftop installations.
The institute also recommended clearer procurement schedules and reverse auctions for large projects. Individual tenders often lack a clear timetable, making preparation harder for developers, lenders and suppliers, it said.
For rooftop systems, the institute proposed setting quotas according to how much power each substation can accommodate. It said the current quota system limits deployment.
Storage and supply face challenges
The electricity plan includes 42.6 gigawatts of renewable energy and 10.3 gigawatts of energy storage. Some transmission infrastructure needed for solar is not scheduled until 2030-2034, the report said.
Domestic solar module production capacity reached 27 gigawatts per year in 2026. More than half needs further verification because of relabeling allegations, according to the report. Cell capacity stands at 14.3 gigawatts.
The United States received 98.2% of Indonesia's solar module exports in 2025. Preliminary US duties of about 104% in February 2026 cut exports to the country by about 98%, the institute said.
Those exports fell from a peak of 2.2 gigawatts in November 2025 to 34 megawatts in April 2026. Final duties of up to 268% followed in September 2026.
Take the quizWhat Kind of Holiday Spender Are You? Take the Black Friday QuizStart →- 1Gold Silver Price November: Futures Rise Near Yearly Lows

- 2Michael Clarke Says Sandpapergate Scars Drew Steve Smith to New York

- 3U.S. Emergency Alert Test Nov. 17 Is Not a Power Outage

- 4Brent Crude Slides 4.05% as Rising US Stockpiles Weigh on Oil

- 52027 NFL Mock Draft Puts Ohio State’s Jeremiah Smith at No. 1

Lifestyle · Food & HealthWhat Is Raynaud’s Syndrome? Why Fingers Turn White in the Cold
Lifestyle · Food & Health4 Ways Walking After Meals Helps Your Body, Doctors Say
Lifestyle · Food & Health4 Reasons to Eat Oatmeal, According to Nutrition Experts
Lifestyle7 Signs Your Social Battery Is Running Low (and Why You Keep Cancelling Plans)