AEMO forecasts 15 TWh for Australia’s data centres
AEMO projects 15 TWh of data centre electricity demand in the NEM by 2029–30, putting grid connection certainty and firming storage at the centre of procurement.

The Australian Energy Market Operator (AEMO) projects data centres could use about 15 TWh in the National Electricity Market by 2029–30, making grid access and firm supply central to project economics. For buyers of Australian colocation infrastructure, AEMO’s data centre power demand forecast makes the case for checking when contracted capacity can actually be delivered.
- AEMO estimates data centres used about 5 TWh in 2025–26 and projects 15 TWh in 2029–30 under Step Change, equivalent to 7.8% of forecast NEM operational consumption (AEMO, 2026 ESOO, p. 38).
- NSW reported up to 28 GW of requested data centre connections in July 2026, with around 13 GW in advanced discussions (NSW Climate and Energy Action).
- AEMO’s Integrated System Plan puts the present value of annualised capital costs at A$106 billion through 2050 under Step Change, including A$6 billion for actionable and future ISP transmission projects (AEMO, 2026 ISP, p. 116).
How AEMO filters the data centre connection queue
AEMO published the 15 TWh figure in its August Electricity Statement of Opportunities (ESOO). That forecast rises to about 34 TWh by 2035–36 under Step Change, or 13% of projected operational consumption. The June Integrated System Plan uses a longer horizon and a different denominator when it puts data centres at almost 10% of NEM underlying demand by 2050. Use the August figures for near-term grid consumption and the June plan for the system investment required across scenarios (AEMO, 2026 ISP, p. 44).
AEMO limits the influence of speculative enquiries by weighting projects according to the likelihood of reaching connection and operation. It uses observed project progression and factors including development status, connection status and developer size, then averages the probability-weighted project forecast with an economic outlook. It also accounts for the gap between maximum connection capacity and actual use, and for the gradual ramp-up after energisation. A campus reserved for future expansion can therefore have a large connection request and a much smaller load in its first operating years (AEMO, August reliability outlook).
For a site shortlist, ask the network business to identify the stage of each connection and the contracted capacity available at each energisation milestone. Ask the operator for the expected site load as tenants take space, including cooling and other facility loads. Those figures let buyers compare a lease’s planned IT capacity with what the site can deliver at handover. For a regional comparison of how power and water shape site selection, see Singapore 200 MW data centre power limits.
What transmission and firming put on the cost sheet
The Integrated System Plan’s least-cost pathway combines renewables, transmission and distribution, storage for firming, and gas backup. Its higher-demand sensitivity finds that faster growth from data centres and other industrial users increases the need for generation and storage and raises the value of transmission. The A$106 billion estimate covers system investment across the NEM. At campus level, request cost and timing estimates for dedicated connection works and identify any upstream upgrades that could determine the energisation date (AEMO, 2026 ISP, pp. 23–25).
| Cost or capacity item | Issuer | Primary-source figure | Procurement implication |
|---|---|---|---|
| NSW entry bond | NSW Government | Proposed A$30,000 per MW of requested capacity | Adds upfront security deposit for large connection applications (NSW consultation) |
| Major network upgrade fee | NSW Government | Interim defaults of A$200,000/MW (Sydney, Newcastle, Wollongong) and A$100,000/MW elsewhere | Requires location-specific network upgrade budgeting (NSW consultation) |
| Renewable supply and storage | NSW Government | 100% renewable match (min. 40% wind) plus 4-hour storage at 25% of generation capacity | Raises contracted firmed-power requirements (NSW Nov briefing) |
| Installed battery reference | NSW Government | 850 MW / 1,680 MWh Waratah Super Battery for grid protection | Demonstrates scale; buyers still need dedicated dispatch rights (NSW Government) |
Use the NSW proposals to stress-test upfront cash needs and compare locations. The national network cost recovery rules and a proposed firmed-energy contracting obligation are separate Australian Energy Market Commission (AEMC) workstreams. The final project-specific connection charge and commercial firming premium are not disclosed in these publications (AEMC, November fact sheet).
When comparing commercial power purchase agreements, ask suppliers to show which hours the contracted portfolio covers and who pays for shortfalls during low renewable output. For battery energy storage systems, specify discharge power, usable energy, recharge rights and dispatch priority. Waratah illustrates why dispatch rights matter. Its published rating describes an asset built to protect the network during disruptions. A buyer needs a contract that specifies the capacity available to its own load and the hours when it can call on it.
How to buy firm capacity and price flexible demand
If latency-sensitive workloads require continuous service, secure firm import capacity for the critical load and make lease payments contingent on agreed energisation milestones. For training jobs that can pause or move, ask for a staged or flexible connection quote. Value any savings against rescheduling costs, tenant commitments and the cost of spare capacity at another site. For an industrial buyer comparing a campus with an expansion of its own plant, ask the network business which upstream works each option depends on and who carries the cost if delivery slips.
Build grid compliance into equipment procurement. The AEMC’s final access rule commenced on 12 November 2026 and generally applies Schedule 5.3 standards automatically to inverter-based loads with an aggregated nameplate rating of at least 30 MW, subject to transitional provisions. Ask suppliers for the equipment models and disturbance response data needed for the connection study before locking in electrical designs (AEMC, final access standards determination).
For industrial energy management software, evaluate whether operators can reconcile connection-point readings with tenant consumption and track excursions against contractual limits. Schneider Electric’s EcoStruxure Power Monitoring Expert is one product to evaluate for power monitoring and load analysis, with Australian project pricing not disclosed on its product page (Schneider Electric). Keep the operational handover broad enough to assign incident escalation and reporting responsibilities alongside metering and dispatch ownership; see the Australia ransomware reporting rule for the separate incident-response requirements.
Release capital against the capacity the network can deliver on a documented date. Size firm supply for the load that must keep running, and price flexibility against workloads that can actually move. That gives treasury a basis for comparing the cost of grid access, storage and residual energy exposure before signing a lease or underwriting a campus.
Take the quizWhat Kind of Holiday Spender Are You? Take the Black Friday QuizStart →- 1U.S. Emergency Alert Test Nov. 17 Is Not a Power Outage

- 2Gold Silver Price November: Futures Rise Near Yearly Lows

- 3Michael Clarke Says Sandpapergate Scars Drew Steve Smith to New York

- 4GTA 6 New Zealand Time Trick Is Not Guaranteed to Work

- 5Sunrise on the Reaping Reviews Split Over Dark Hunger Games Prequel

Lifestyle · Food & Health4 Reasons to Eat Oatmeal, According to Nutrition Experts
Lifestyle7 Signs Your Social Battery Is Running Low (and Why You Keep Cancelling Plans)
Lifestyle · Food & HealthThanksgiving Food Safety: How Long Leftovers Last and the Safe Turkey Temperature
Lifestyle7 Quiet Habits of Emotionally Intelligent People, According to Psychologists















